· Expressways · National highways · Infrastructure
The Expressways That Opened in 2026: Nine Openings and Their Caveats
Written and checked byRamanathan Virli· Roads & Infrastructure
Key points
- Three complete corridors were inaugurated: Ahmedabad–Dholera (31 March), Delhi–Dehradun (14 April) and the 594 km Ganga Expressway (29 April).
- Lucknow–Kanpur (NE-6) was inaugurated on 13 July, and the 162 km Khammam–Devarapalli highway opened to traffic on 2 August.
- The Delhi–Amritsar–Katra Expressway’s first ~189 km opened on 17 July; the rest is under construction.
- On the Delhi–Mumbai Expressway, the 55 km Limkheda–Godhra section opened officially in October, leaving one gap in Gujarat.
- The Mumbai–Pune Missing Link opened on 1 May, then had a landslide closure in July.
The openings at a glance
Dates are those of the inauguration or, where there was none, the day traffic was let on. Lengths are those stated by the government or in the reporting cited below.
| Date | Expressway | What opened | State(s) |
|---|---|---|---|
| 31 Mar | Ahmedabad–Dholera Expressway | Inaugurated by the Prime Minister | Gujarat |
| 14 Apr | Delhi–Dehradun Economic Corridor | 213 km, six-lane, inaugurated in Dehradun | Delhi, Uttar Pradesh, Uttarakhand |
| 29 Apr | Ganga Expressway | 594 km, Meerut to Prayagraj, inaugurated in Hardoi | Uttar Pradesh |
| 1 May | Mumbai–Pune Expressway Missing Link | 13.3 km, Khopoli to Kusgaon, bypassing the Bhor ghat | Maharashtra |
| Late Jun | Bengaluru–Chennai Expressway (NE-7) | 25 km, Bethamangala to Baireddypalle; about 100 km now open from Hoskote | Karnataka, Andhra Pradesh |
| 13 Jul | Lucknow–Kanpur Expressway (NE-6) | 63 km, full route | Uttar Pradesh |
| 17 Jul | Delhi–Amritsar–Katra Expressway | Packages 1–5 (157.92 km, Haryana) and Package 6 (30.9 km, Punjab) | Haryana, Punjab |
| 2 Aug | Khammam–Devarapalli (NH-365BG) | 162.04 km, opened to traffic before formal inauguration | Telangana, Andhra Pradesh |
| Oct | Delhi–Mumbai Expressway | 55 km, Limkheda to Godhra (Packages 27 and 28), after two months of trial running | Gujarat |
The complete corridors
Delhi–Dehradun is the best documented. Releases from the Prime Minister’s Office describe a 213 km six-lane access-controlled corridor built at a cost of over ₹12,000 crore. It runs through Delhi, Uttar Pradesh and Uttarakhand and cuts the Delhi–Dehradun journey from over six hours to around two and a half.
The Ganga Expressway runs 594 km from Meerut to Prayagraj, entirely within Uttar Pradesh. The Lucknow–Kanpur Expressway, also called the Awadh Expressway or NE-6, is 63 km long. It combines an 18 km elevated section in Lucknow with a 45 km greenfield stretch. Ahmedabad–Dholera links Ahmedabad with the Dholera Special Investment Region and was inaugurated on 31 March at a reported cost of more than ₹5,100 crore.
Openings that come with caveats
- Mumbai–Pune Missing Link: opened by the Maharashtra Chief Minister on 1 May 2026. In early July, a landslide near the exit of Tunnel 2 closed the Mumbai-bound carriageway for more than 18 hours, and lanes reopened only in stages. MSRDC said it would ask IIT Bombay for a fresh safety study. Check MSRDC advisories before monsoon travel.
- Khammam–Devarapalli: the 162.04 km corridor was opened to motorists unofficially on 2 August 2026, from Tallampadu, once the Dhamsalapuram railway overbridges were finished. Toll collection was to start only after a formal inauguration.
- Delhi–Mumbai, Limkheda–Godhra: the section ran on a trial basis from August and was reported as officially open in mid-October. The same report said the Limkheda toll plaza would start collecting from 1 November, and that there were no fuel stations or restaurants on the stretch yet.
- Bengaluru–Chennai: the 25 km Bethamangala–Baireddypalle section was reported open on 29 June 2026, with toll charges announced. The remaining Andhra Pradesh and Tamil Nadu packages are still under construction.
Still unfinished
On the Delhi–Mumbai Expressway, the remaining gap in this stretch is Package 26, between Limkheda and the Madhya Pradesh border. It was reported as due by December 2026 or January 2027, and finishing it would join the route from Delhi to Kharel in Navsari. The Delhi–Amritsar–Katra Expressway still has its Punjab and Jammu and Kashmir packages to finish. Our expressway pages keep the current status of each.